17.03.2015 – commencement of construction
21.03.2015 – foundation excavation
03.03.2015 – concrete levelling of foundations
22.04.2015 – completion of foundation slab
17.05.2015 – completed construction of Storey 1 ceiling
06.06.2015 – completed construction of Storey 2 ceiling
30.06.2015 – completed construction of Storey 3 ceiling
23.07.2015 – completed construction of Storey 4 ceiling
07.09.2015 – completed construction of Storey 5 ceiling
since 17.08.2015 – facade works are under way
24.05.2016 - End of construction work
14.07.2016 - Aquaring certificate of occupancy